European Union · Question · QUESTION_WRITTEN
E-10-2025-002722
Execução do projeto de ligação transfronteiriça Portugal–Espanha, em Alcoutim, previsto no Plano de Recuperação e Resiliência, além do prazo de 30.06.2026
Introduced
3 July 2025
Last action
1 August 2025 · Answer
Status
answered
Sponsors
Isilda GOMES
Subjects
Discovery layer
Source updated
1 August 2025
Records
Official question E-10-2025-002722 from European Union at European Parliament. Dated 3 July 2025. Status: answered.
Timeline
3 July 2025
Written question
Execução do projeto de ligação transfronteiriça Portugal–Espanha, em Alcoutim, previsto no Plano de Recuperação e Resiliência, além do prazo de 30.06.2026
Source: QUESTION_WRITTEN
1 August 2025
Answer
Source: QUESTION_WRITTEN_ANSWER
Votes
No vote records are attached yet.
Versions
No version snapshots stored. Document URLs remain at the source.
Documents
5 official files
Answer
This file cannot be previewed here. Use View or Download.
Reading translation
Translate this document into your language. PoliticalRepo does not store a separate copy per EU language.
On-demand whole-document translation with a downloadable PDF (logo + link to the official source). The official file stays authoritative.
Answer
QUESTION_WRITTEN_ANSWER · 1 August 2025
Portugal-Spain cross-border connection project in Alcoutim and recovery and resilience plan deadline of 30 June 2026
QUESTION_WRITTEN · EN · 10 July 2025
DownloadOpen at official source
Leesvertaling
Vertaal dit document naar jouw taal. PoliticalRepo bewaart geen aparte kopie per EU-taal.
Documentvertaling op verzoek met downloadbare PDF (logo + link naar de officiële bron). Het bronbestand blijft leidend.
Portugal-Spain cross-border connection project in Alcoutim and recovery and resilience plan deadline of 30 June 2026
QUESTION_WRITTEN · EN · 10 July 2025
ViewDownloadOpen at official source
Leesvertaling
Vertaal dit document naar jouw taal. PoliticalRepo bewaart geen aparte kopie per EU-taal.
Documentvertaling op verzoek met downloadbare PDF (logo + link naar de officiële bron). Het bronbestand blijft leidend.
Execução do projeto de ligação transfronteiriça Portugal–Espanha, em Alcoutim, previsto no Plano de Recuperação e Resiliência, além do prazo de 30.06.2026
QUESTION_WRITTEN · PT · 10 July 2025
DownloadOpen at official source
Reading translation
Translate this document into your language. PoliticalRepo does not store a separate copy per EU language.
On-demand whole-document translation with a downloadable PDF (logo + link to the official source). The official file stays authoritative.
Execução do projeto de ligação transfronteiriça Portugal–Espanha, em Alcoutim, previsto no Plano de Recuperação e Resiliência, além do prazo de 30.06.2026
QUESTION_WRITTEN · PT · 10 July 2025
ViewDownloadOpen at official source
Reading translation
Translate this document into your language. PoliticalRepo does not store a separate copy per EU language.
On-demand whole-document translation with a downloadable PDF (logo + link to the official source). The official file stays authoritative.
Sponsors
- · COM · ADDRESSEE
- Isilda GOMES · AUTHOR
Related records
No cross-record relationships stored yet.
Sources
PoliticalRepo is an index and interpretation layer, not the authoritative legal source.
- Official source: https://www.europarl.europa.eu/doceo/document/E-10-2025-002722_EN.html
- Open data entity: https://data.europarl.europa.eu/api/v2/parliamentary-questions/E-10-2025-002722
- eu · E-10-2025-002722 · source updated 1 August 2025