Attuazione del progetto tramviario di Bologna finanziato nell'ambito del PNRR e conseguenze derivanti da incrementi dei costi e ritardi nell'esecuzione
Introduced
15 July 2026
Last action
—
Status
QUESTION_WRITTEN
Sponsors
—
Subjects
Discovery layer
Source updated
15 July 2026
Records
Official question E-10-2026-002944 from European Union at European Parliament. Dated 15 July 2026. Status: QUESTION_WRITTEN.
Timeline
No timeline events have been ingested for this record yet.
Votes
No vote records are attached yet.
Versions
No version snapshots stored. Document URLs remain at the source.
Documents
4 official files
Construction of the NRRP-funded Bologna tram network and the implications of potential cost increases and delays
This file cannot be previewed here. Use View or Download.
Construction of the NRRP-funded Bologna tram network and the implications of potential cost increases and delays
QUESTION_WRITTEN · EN · 23 July 2026
Construction of the NRRP-funded Bologna tram network and the implications of potential cost increases and delays
QUESTION_WRITTEN · EN · 23 July 2026
Attuazione del progetto tramviario di Bologna finanziato nell'ambito del PNRR e conseguenze derivanti da incrementi dei costi e ritardi nell'esecuzione
QUESTION_WRITTEN · IT · 23 July 2026
Attuazione del progetto tramviario di Bologna finanziato nell'ambito del PNRR e conseguenze derivanti da incrementi dei costi e ritardi nell'esecuzione
QUESTION_WRITTEN · IT · 23 July 2026
Sponsors