PQ 29
23 Deputy Simon Coveney asked the Minister for Health and Children if, taking into account that the new children’s hospital is projected to cost approximately €1 billion, this project is being reviewed in view of the difficult financial state here; if she plans to review this project; if not, if she has the necessary funding committed to complete this project; the completion date for this project; the yearly funds necessary for the completion of this project; and if she will make a statement on the matter. [6633/09]
Introduced
19 February 2009
Last action
—
Status
written
Sponsors
—
Subjects
Discovery layer
Source updated
19 February 2009
Summary
23 Deputy Simon Coveney asked the Minister for Health and Children if, taking into account that the new children’s hospital is projected to cost approximately €1 billion, this project is being reviewed in view of the difficult financial state here; if she plans to review this project; if not, if she has the necessary funding committed to complete this project; the completion date for this project; the yearly funds necessary for the completion of this project; and if she will make a statement on the matter. [6633/09]
This text is taken from the official record. PoliticalRepo does not editorialize.
Timeline
No timeline events have been ingested for this record yet.
Votes
No vote records are attached yet.
Versions
No version snapshots stored. Document URLs remain at the source.
Documents
1 official file
Hospitals Building Programme.
Hospitals Building Programme.
xml · EN · 19 February 2009
Sponsors
No sponsors or actors listed by the source.
Related records
No cross-record relationships stored yet.
Sources
PoliticalRepo is an index and interpretation layer, not the authoritative legal source.
- Official source: https://www.oireachtas.ie/en/debates/question/2009-02-19/29/
- Open data entity: https://data.oireachtas.ie/ie/oireachtas/question/2009-02-19/pq_29