Question· Written questionHL HL1147answered
United Kingdom · UK Parliament · 21 June 2022
To ask the Parliamentary Works Sponsor Body what has been the cost of the work on the Restoration and Renewal programme since 2012 in respect of (1) the salaries, recruitment fees, and redundancy payments for non-parliamentary staff, such as those working
Question· Written questionHL HL725answered
United Kingdom · UK Parliament · 7 June 2022
To ask the Parliamentary Works Sponsor Body how much money they have spent so far on drawing up plans for the Restoration and Renewal of the Houses of Parliament.
Question· Written questionHL HL296answered
United Kingdom · UK Parliament · 17 May 2022
To ask the Parliamentary Works Sponsor Body how much has been spent to date on the proposed decant of the House of Lords to the Queen Elizabeth II conference centre during the Restoration and Renewal works.
Question· Written questionUIN 137243answered
United Kingdom · UK Parliament · 9 March 2022
To ask the Right hon. Member for Alyn and Deeside representing the Parliamentary Works Sponsor Body, what steps the Sponsor Body is taking to help ensure that the construction of the Holocaust Memorial Centre is conducted sustainably.
Question· Written questionUIN 137247answered
United Kingdom · UK Parliament · 9 March 2022
To ask the Right hon. Member for Alyn and Deeside representing the Parliamentary Works Sponsor Body, what steps the Sponsor body is taking to help mitigate road pollution on and around the Parliamentary estate during restoration and renewal works.
Question· Written questionUIN 137245answered
United Kingdom · UK Parliament · 9 March 2022
To ask the Right hon. Member for Alyn and Deeside representing the Parliamentary Works Sponsor Body, what assessment the Sponsor Body has made of the potential impact of the Restoration and Renewal of the Parliamentary Estate on levels of air pollution.
Question· Written questionUIN 137248answered
United Kingdom · UK Parliament · 9 March 2022
To ask the Right hon. Member for Alyn and Deeside representing the Parliamentary Works Sponsor Body, what discussions the Sponsor Body has had with (a) experts and (b) industry leaders in (i) haulage and (ii) construction to ensure that the River Thames i
Question· Written questionUIN 137246answered
United Kingdom · UK Parliament · 9 March 2022
To ask the Right hon. Member for Alyn and Deeside representing the Parliamentary Works Sponsor Body, what assessment the Sponsor Body has made of the potential merits of transporting construction materials and debris via the River Thames during the (a) co
Question· Written questionUIN 119501answered
United Kingdom · UK Parliament · 7 February 2022
To ask the Right hon. Member for Alyn and Deeside representing the Parliamentary Works Sponsor Body, what the monthly operating costs are of the Restoration and Renewal Programme, (a) in total and (b) by spending on (i) employment/salaries, (ii) planning
Question· Written questionUIN 119500answered
United Kingdom · UK Parliament · 7 February 2022
To ask the Right hon. Member for Alyn and Deeside representing the Parliamentary Works Sponsor Body, what the latest estimate is that the Delivery Authority has submitted to the Parliamentary Works Sponsor Body regarding the overall cost of the Restoratio
Question· Written questionUIN 137244withdrawn
United Kingdom · UK Parliament · 9 March 2022
To ask the Right hon. Member for Alyn and Deeside representing the Parliamentary Works Sponsor Body, what steps the Sponsor Body is taking to mitigate road traffic pollution caused by restoration and renewal on the parliamentary estate.
Question· Written questionHL HL14480answered
United Kingdom · UK Parliament · 22 March 2021
To ask the Parliamentary Works Sponsor Body, further to the remarks by the Leader of the House of Commons on 11 March (HC Deb, col 1006), what discussions they have had with him about reports of the costs of the refurbishment of the Palace of Westminster;
Question· Written questionHL HL13939answered
United Kingdom · UK Parliament · 4 March 2021
To ask the Parliamentary Works Sponsor Body (1) what plans they have to publish all submissions to the review of the Restoration and Renewal Programme received from Members of both Houses of Parliament and those outside Parliament, (2) if they have such p
Question· Written questionUIN 163307answered
United Kingdom · UK Parliament · 4 March 2021
To ask the Right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, whether the Sponsor Body has made an assessment of the potential effect of the completion of ongoing fire safety works on the cost of the restoration and r
Question· Written questionUIN 163305answered
United Kingdom · UK Parliament · 4 March 2021
To ask the Right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what advice the Sponsor Body has sought from (a) the Infrastructure and Projects Authority, (b) HM Treasury and (c) the National Audit Office on the costs
Question· Written questionUIN 151715answered
United Kingdom · UK Parliament · 9 February 2021
To ask the Right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what assessment the body has made of the viability of Church House as a temporary replacement for the Palace of Westminster while it undergoes essential re
Question· Written questionUIN 151882answered
United Kingdom · UK Parliament · 9 February 2021
To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what the costs are for the (a) business planning and (b) other preliminary works for the Restoration and Renewal Programme before the full works programme
Question· Written questionUIN 151884answered
United Kingdom · UK Parliament · 9 February 2021
To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, how many staff are employed on the Restoration and Renewal programme; and what the average cost, including employer national insurance and pension contribu
Question· Written questionUIN 142997answered
United Kingdom · UK Parliament · 25 January 2021
To ask the Right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what the timetable is for the publication of the Strategic Review on Renewal and Restoration.
Question· Written questionUIN 128054answered
United Kingdom · UK Parliament · 10 December 2020
To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what discussions he has had with (a) Ministers and the (b) House of Commons Commission on the effect of the parliamentary restoration and renewal project o
Question· Written questionUIN 128055answered
United Kingdom · UK Parliament · 10 December 2020
To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what steps he is taking to mitigate the effect of the parliamentary restoration and renewal project on roadside air pollution in London.
Question· Written questionUIN 114768answered
United Kingdom · UK Parliament · 12 November 2020
To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what assessment of air quality has been made as part of the plans for refurbishing the Palace of Westminster.
Question· Written questionHL HL9303answered
United Kingdom · UK Parliament · 19 October 2020
To ask the Parliamentary Works Sponsor Body what discussions they have had about (1) the combining, and (2) the rationalising, of facilities as part of the Palace of Westminster Restoration and Renewal Programme, including of (a) libraries, (b) refreshmen
Question· Written questionHL HL7835answered
United Kingdom · UK Parliament · 3 September 2020
To ask the Parliamentary Works Sponsor Body what plans they have to conduct an independent review (1) of the costs and benefits of the restoration and renewal scheme for the Palace of Westminster, and (2) of the attendant costs and benefits of decanting M
Question· Written questionHL HL6484answered
United Kingdom · UK Parliament · 6 July 2020
To ask the Parliamentary Works Sponsor Body whether the Strategic Review of the Restoration and Renewal Programme will be conducted by one person, or corporately by the Sponsor Body.
Question· Written questionUIN 55862answered
United Kingdom · UK Parliament · 8 June 2020
To ask the Right hon. Member for East Hampshire representing the Parliamentary Works Sponsor Body, with reference to the Houses of Parliament Restoration and Renewal press release published on 19 May 2020, what the names are of the people appointed to the
Question· Written questionUIN 48280answered
United Kingdom · UK Parliament · 18 May 2020
To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what steps he will take to minimise air pollution in central London from the Restoration and Renewal project on the Palace of Westminster.
Question· Written questionUIN 48279answered
United Kingdom · UK Parliament · 18 May 2020
To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, whether an environmental impact assessment has been carried out for the Restoration and Renewal project on the Palace of Westminster.
Question· Written questionUIN 48275answered
United Kingdom · UK Parliament · 18 May 2020
To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what assessment he has made of the potential merits of moving freight to and from the Restoration and Renewal construction site at the Palace of Westminste
Question· Written questionUIN 45120answered
United Kingdom · UK Parliament · 7 May 2020
To ask the Right hon. Member for East Hampshire representing the Parliamentary Works Sponsor Body, what assessment he has made of the merits of including (a) swift bricks, (b) bird boxes, (c) beehives, and (d) others in the refurbishment of the Palace of
Report· Written statementUIN HLWS611published
United Kingdom · UK Parliament · 23 February 2022
The Parliamentary Works Sponsor Body has today deposited a paper in the Library of both Houses, entitled 'Essential Scheme: Initial Assessment of Cost and Schedule; and Continued Presence: Impact Study', following the request of the House of Commons Commi...
Report· Written statementUIN HCWS626published
United Kingdom · UK Parliament · 23 February 2022
The Parliamentary Works Sponsor Body has today deposited a paper in the Library of both Houses, entitled 'Essential Scheme: Initial Assessment of Cost and Schedule; and Continued Presence: Impact Study', following the request of the House of Commons Commi...
Report· Written statementUIN HLWS221published
United Kingdom · UK Parliament · 21 July 2021
I wish to inform the House that I have been appointed by the Parliamentary Works Sponsor Body as its new spokesperson in the House of Lords. I take over this role from Baroness Scott of Needham Market, who has held the role since the Sponsor Body became a...
Report· Written statementUIN HLWS831published
United Kingdom · UK Parliament · 11 March 2021
In May 2020 the Sponsor Body established a Strategic Review of the Restoration and Renewal Programme.The purpose of the review was to consider whether anything had changed so significantly as to warrant a change in the strategy for the Restoration and Ren...
Report· Written statementUIN HCWS839published
United Kingdom · UK Parliament · 11 March 2021
In May 2020 the Sponsor Body established a Strategic Review of the Restoration and Renewal Programme.The purpose of the review was to consider whether anything had changed so significantly as to warrant a change in the strategy for the Restoration and Ren...
Report· Written statementUIN HLWS321published
United Kingdom · UK Parliament · 1 July 2020
Following the announcment of its intention to conduct a strategic review of the Restoration and Renewal Programme, today the Sponsor Body invites Members of the House and their staff to submit their views to inform our review.Members and Members' staff ar...
Report· Written statementUIN HCWS328published
United Kingdom · UK Parliament · 1 July 2020
Following the announcment of its intention to conduct a strategic review of the Restoration and Renewal Programme, today the Sponsor Body invites Members of the House and their staff to submit their views to inform our review.Members and Members' staff ar...
Report· Written statementUIN HLWS250published
United Kingdom · UK Parliament · 2 June 2020
I wish to infiorn the House regarding certain documents that have been agreed by virtue of the Parliamentary Buildings (Restoration and Renewal) Act 2019 ('the Act').On 8 April the Parliamentary Works Sponsor Body was established as a corporate body by se...
Report· Written statementUIN HCWS254published
United Kingdom · UK Parliament · 2 June 2020
I wish to inform the House regarding certain documents that have been agreed by virtue of the Parliamentary Buildings (Restoration and Renewal) Act 2019 ('the Act').On 8 April the Parliamentary Works Sponsor Body was established as a corporate body by sec...