Summary

To ask the Senior Deputy Speaker, further to his Written Answers on 30 January (HL4799) and 13 February (HL5334), which stakeholders requested traffic marshals prior to their introduction and to whom those requests were communicated.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 5 September 2023

    Written question

    To ask the Senior Deputy Speaker, further to his Written Answers on 30 January (HL4799) and 13 February (HL5334), which stakeholders requested traffic marshals prior to their introduction and to whom those requests were communicated.

    Source: Lords

  2. 19 September 2023

    Answer

    A wide range of stakeholders were engaged before the implementation of the one-way traffic management system by Strategic Estates Construction Management Team. The key stakeholder groups were Parliamentary Safety Assurance Board (PSAB) and the Logistics S...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.