PoliticalRepoPoliticalRepo

United Kingdom · Question · Written question

UIN 101608

Ajax Vehicles: Procurement

answeredUnited Kingdom· UK Parliament· EN

Introduced

18 December 2025

Last action

8 January 2026 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

8 January 2026

Summary

To ask the Secretary of State for Defence, what value of contract stage payment claim by General Dynamics was triggered by declaring Initial Operating Capability (IOC) for Ajax in November, and whether his department has paid it yet.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 18 December 2025

    Written question

    To ask the Secretary of State for Defence, what value of contract stage payment claim by General Dynamics was triggered by declaring Initial Operating Capability (IOC) for Ajax in November, and whether his department has paid it yet.

    Source: Commons

  2. 8 January 2026

    Answer

    There was no specific payment to General Dynamics related to Initial Operating Capability.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.