Challenger Tanks: Procurement

answeredUnited Kingdom· UK Parliament· EN

Introduced

16 June 2026

Last action

24 June 2026 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

24 June 2026

Summary

To ask the Secretary of State for Defence, when will the Challenger 3 programme reach (a) Initial Operating Capability and (b) Full Operating Capability.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 16 June 2026

    Written question

    To ask the Secretary of State for Defence, when will the Challenger 3 programme reach (a) Initial Operating Capability and (b) Full Operating Capability.

    Source: Commons

  2. 24 June 2026

    Answer

    The Challenger 3 manufacture phase timing will be confirmed after the demonstration phase trials prove the performance of the tanks. This complex programme has been impacted by some supply chain delays; the Initial Operating Capability and Full Operating ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.