To ask the Secretary of State for Transport, with reference to her Department's press release entitled PM redirects HS2 funding to revolutionise transport across the North and Midlands, published of 04 October 2023, what is the estimated cost to the publi

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 21 October 2024

    Written question

    To ask the Secretary of State for Transport, with reference to her Department's press release entitled PM redirects HS2 funding to revolutionise transport across the North and Midlands, published of 04 October 2023, what is the estimated cost to the publi

    Source: Commons

  2. 24 October 2024

    Answer

    The Department is currently assessing the cost of cancelling Phase 2 of the HS2 project, working with HS2 Ltd and its supply chain to inform this assessment. As at the end of March 2024, £2.3bn had been spent on Phase 2.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.