Summary

To ask the Secretary of State for Defence, with reference to table one and corresponding note five of his Department's publication MOD trade industry and contracts data tables 2023, published on 28 September 2023, for what reason the forecast costs of the

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 9 November 2023

    Written question

    To ask the Secretary of State for Defence, with reference to table one and corresponding note five of his Department's publication MOD trade industry and contracts data tables 2023, published on 28 September 2023, for what reason the forecast costs of the

    Source: Commons

  2. 20 November 2023

    Answer

    The additional £449.56 million forecast cost to the Mechanised Infantry Vehicle programme is a result of the increase in scope to enhance and uplift the fleet sizes and capabilities, as set out in the Defence Command Plan (2021).This includes funding for ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.