Summary

To ask the Secretary of State for Business, Energy and Industrial Strategy, what assessment he has made of the (a) grid infrastructure upgrades required to facilitate the planned deployment of 40GW of offshore wind by 2030 and (b) effect of Ofgem's inter

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 14 October 2020

    Written question

    To ask the Secretary of State for Business, Energy and Industrial Strategy, what assessment he has made of the (a) grid infrastructure upgrades required to facilitate the planned deployment of 40GW of offshore wind by 2030 and (b) effect of Ofgem's inter

    Source: Commons

  2. 19 October 2020

    Answer

    In July, the Government launched the Offshore Transmission Network Review to assess the approach to delivering connections for offshore wind. As part of this review, National Grid ESO is consulting on their cost-benefit analysis of a more coordinated appr...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.