M6: Repairs and Maintenance

answeredUnited Kingdom· UK Parliament· EN

Introduced

12 January 2026

Last action

20 January 2026 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

20 January 2026

Summary

To ask the Secretary of State for Transport, when any assessment by National Highways of temporary slip roads at Junction 38 of the M6 was undertaken; and whether the findings of that assessment informed the current construction programme.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 12 January 2026

    Written question

    To ask the Secretary of State for Transport, when any assessment by National Highways of temporary slip roads at Junction 38 of the M6 was undertaken; and whether the findings of that assessment informed the current construction programme.

    Source: Commons

  2. 20 January 2026

    Answer

    National Highways first assessed the potential for temporary slip roads during the project’s optioneering stage in 2019. Further consideration took place during early design development, and the option was not taken forward at that time due to spatial con...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.