To ask the Secretary of State for Transport, pursuant to the Answer of 6 January 2026 to Question 98750, when the A12 widening scheme was deferred by the previous Government; on what date that decision was taken; what effect that decision had on the statu

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 20 January 2026

    Written question

    To ask the Secretary of State for Transport, pursuant to the Answer of 6 January 2026 to Question 98750, when the A12 widening scheme was deferred by the previous Government; on what date that decision was taken; what effect that decision had on the statu

    Source: Commons

  2. 10 February 2026

    Answer

    A decision was taken in March 2024 to defer the start of construction on the A12 widening scheme. This had no impact on the statutory Development Consent Order as consent had been granted in January 2024.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.