Mount Vernon Hospital Northwood: Radiotherapy

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

3 February 2020

Last action

11 February 2020 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

11 February 2020

Summary

To ask the Secretary of State for Health and Social Care, what the estimated cost to the public purse is of (a) replacing and (b) relocating the Linear Accelerators on the Mount Vernon site to another location, and if he will make a statement.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 3 February 2020

    Written question

    To ask the Secretary of State for Health and Social Care, what the estimated cost to the public purse is of (a) replacing and (b) relocating the Linear Accelerators on the Mount Vernon site to another location, and if he will make a statement.

    Source: Commons

  2. 11 February 2020

    Answer

    The estimated cost to replace a Linear Accelerator in its current location is approximately £1.5 million. Relocation costs vary depending on preparations required and where the Linear Accelerator is being relocated to. Relocation to a site with a ready-to...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.