PoliticalRepoPoliticalRepo

United Kingdom · Question · Written question

UIN 118015

Electric Cables

answeredUnited Kingdom· UK Parliament· EN

Introduced

4 March 2026

Last action

9 March 2026 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

9 March 2026

Summary

To ask the Secretary of State for Energy Security and Net Zero, what estimate he has made of the costs of (a) undergrounding electricity transmission infrastructure and (b) developing overhead transmission lines.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 4 March 2026

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, what estimate he has made of the costs of (a) undergrounding electricity transmission infrastructure and (b) developing overhead transmission lines.

    Source: Commons

  2. 9 March 2026

    Answer

    Evidence published by the Institution of Engineering and Technology (April 2025) shows that the lifetime cost of underground transmission cables is around four and a half times higher than overhead lines. As costs are borne by the electricity bill payer, ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.