United Kingdom · Question · Written question

UIN 12775

EDF Group

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

2 February 2024

Last action

12 February 2024 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

12 February 2024

Summary

To ask the Secretary of State for Energy Security and Net Zero, with reference to EDF's media release entitled January 2024 project update, published on 23 January 2024], whether her Department had discussions on the scale of (a) overruns and (b) overspen

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 2 February 2024

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, with reference to EDF's media release entitled January 2024 project update, published on 23 January 2024], whether her Department had discussions on the scale of (a) overruns and (b) overspen

    Source: Commons

  2. 12 February 2024

    Answer

    Hinkley Point C (HPC) is not a Government project and its financing is a matter for EDF and its shareholders. The Department engages regularly with EDF on HPC’s progress and related matters. Officials were aware the HPC were likely to make an update to co...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.