To ask the Secretary of State for Energy Security and Net Zero, what her Department's latest estimate is of the capital expenditure cost of a new 1GW blue hydrogen plant commissioning by 2030.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 5 February 2024

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, what her Department's latest estimate is of the capital expenditure cost of a new 1GW blue hydrogen plant commissioning by 2030.

    Source: Commons

  2. 13 February 2024

    Answer

    ‘Hydrogen Production Costs 2021’, published by the Department for Business, Energy and Industrial Strategy in August 2021, sets out the levelised cost of various hydrogen production technologies. The information requested can be found in the table ‘Techni...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.