To ask the Secretary of State for Transport, what consideration his department has given to reducing the 6-month grace period that utility companies have to undertake full repairs to paving in town centres.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 26 June 2026

    Written question

    To ask the Secretary of State for Transport, what consideration his department has given to reducing the 6-month grace period that utility companies have to undertake full repairs to paving in town centres.

    Source: Commons

  2. 1 July 2026

    Answer

    Statutory guidance already makes clear that permanent reinstatements should be completed by utility companies as soon as reasonably practicable and that, where an interim reinstatement is used, it should normally be made permanent within six months.The De...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.