To ask the Secretary of State for Energy Security and Net Zero, if she will have discussions with National Grid on ensuring that the statutory consultation on the Norwich to Tilbury infrastructure project does not take place until the Electricity System O

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 16 February 2024

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, if she will have discussions with National Grid on ensuring that the statutory consultation on the Norwich to Tilbury infrastructure project does not take place until the Electricity System O

    Source: Commons

  2. 21 February 2024

    Answer

    As the statutory consultation process is not led by Government, there have not been discussions between the Secretary of State and National Grid Electricity Transmission (NGET) on the timing and alignment of its consultation on this project. NGET has howe...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.