Typhoon Aircraft: Training

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

4 March 2024

Last action

13 March 2024 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

13 March 2024

Summary

To ask the Secretary of State for Defence, with reference to page 121 of his Department's Annual Report and Accounts 2022-23, for what reason the fruitless payment relating to the Reconstruction of Multi Threat Wall for Typhoon Synthetic Trainers was made

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 4 March 2024

    Written question

    To ask the Secretary of State for Defence, with reference to page 121 of his Department's Annual Report and Accounts 2022-23, for what reason the fruitless payment relating to the Reconstruction of Multi Threat Wall for Typhoon Synthetic Trainers was made

    Source: Commons

  2. 13 March 2024

    Answer

    Additional costs were incurred on the Typhoon Future Synthetic Training new buildings to ensure the internal walls complied with the latest appropriate standards, in order to meet security requirements.This required the redesign and rework of walls that w...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.