To ask the Secretary of State for Transport, pursuant to the Answer of 21 March 2023 to Question 163903 on Euston Station: High Speed 2 Line, how much from the public purse has been spent on HS2 works relating to Euston station as of 27 March 2023.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 27 March 2023

    Written question

    To ask the Secretary of State for Transport, pursuant to the Answer of 21 March 2023 to Question 163903 on Euston Station: High Speed 2 Line, how much from the public purse has been spent on HS2 works relating to Euston station as of 27 March 2023.

    Source: Commons

  2. 30 March 2023

    Answer

    The most recent costs for Euston are as reported in the NAO report that was published on 27 March 2023, which are £548m on design and preliminary works and £1.5Bn on enabling works and land & property costs for the station and the surrounding area.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.