Railways: North of England

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

25 March 2021

Last action

19 April 2021 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

19 April 2021

Summary

To ask the Secretary of State for Transport, pursuant to the Answer of 23 March 2021 to Question 171706 on Railways: North of England, what plans he has to electrify the route between Leeds and York via Cross Gates and Garforth.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 25 March 2021

    Written question

    To ask the Secretary of State for Transport, pursuant to the Answer of 23 March 2021 to Question 171706 on Railways: North of England, what plans he has to electrify the route between Leeds and York via Cross Gates and Garforth.

    Source: Commons

  2. 19 April 2021

    Answer

    £589m funding announced in July 2020 has enabled further development of electrification design for the section between Church Fenton and York. We are actively reviewing the case for TRU to deliver full electrification on the route, with construction decis...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.