PoliticalRepoPoliticalRepo

United Kingdom · Question · Written question

UIN 176728

Boiler Upgrade Scheme

answeredUnited Kingdom· UK Parliament· EN

Introduced

29 March 2023

Last action

21 April 2023 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

21 April 2023

Summary

To ask the Secretary of State for Energy Security and Net Zero, whether underspend from the first year of the Boiler Upgrade Scheme will be returned to the Treasury.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 29 March 2023

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, whether underspend from the first year of the Boiler Upgrade Scheme will be returned to the Treasury.

    Source: Commons

  2. 21 April 2023

    Answer

    The Boiler Upgrade Scheme (BUS) budget is £450 million, split equally over three financial years (2022-2025). The Government explored options to carry over unused budget from year 1 of the scheme, but due to the accounting rules for capital spending, the ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.