To ask the Secretary of State for Energy Security and Net Zero, what discussions she has had with the National Grid on improving the timetable for connecting infrastructure projects to the national grid.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 8 March 2024

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, what discussions she has had with the National Grid on improving the timetable for connecting infrastructure projects to the national grid.

    Source: Commons

  2. 13 March 2024

    Answer

    The Government is working with Ofgem, the Electricity System Operator and network companies to accelerate network connections. Since the Connections Action Plan[1] was published in November 2023, over 40GW of projects have been offered earlier grid connec...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.