Wind Power: Seas and Oceans

answeredUnited Kingdom· UK Parliament· EN

Introduced

11 March 2024

Last action

14 March 2024 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

14 March 2024

Summary

To ask the Secretary of State for Energy Security and Net Zero, if she will make an estimate of the potential additional costs for offshoring the required new grid capacity between north east (a) Scotland and (b) England.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 11 March 2024

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, if she will make an estimate of the potential additional costs for offshoring the required new grid capacity between north east (a) Scotland and (b) England.

    Source: Commons

  2. 14 March 2024

    Answer

    Electricity network planning is a function of the independent Electricity System Operator (ESO). Through the Holistic Network Design (HND), the transitional Centralised Strategic Network Plan and in the future through the Centralised Strategic Network Pla...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.