To ask the Secretary of State for Defence, whether his Department plans to put in place a monitoring framework following the completion of the remediation works at Dalgety Bay.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 19 April 2023

    Written question

    To ask the Secretary of State for Defence, whether his Department plans to put in place a monitoring framework following the completion of the remediation works at Dalgety Bay.

    Source: Commons

  2. 24 April 2023

    Answer

    Ministry of Defence Officials will continue monitoring the beach at Dalgety Bay for two years after completion of the remediation works. This has been agreed with the Scottish Environment Protection Agency (SEPA) in order to prove the success of the works...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.