To ask the Secretary of State for Energy Security and Net Zero, what steps his Department is taking to construct grid connections for Sizewell C.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 9 December 2024

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, what steps his Department is taking to construct grid connections for Sizewell C.

    Source: Commons

  2. 17 December 2024

    Answer

    The policy position outlined in the National Energy System Operator (“NESO”) open letter [https://www.neso.energy/document/349496/download] (published 10th December 2024) indicates that, given Sizewell C received planning consent in July 2022, the existin...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.