Fleet Solid Support Ships: Procurement

answeredUnited Kingdom· UK Parliament· EN

Introduced

17 July 2023

Last action

20 July 2023 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

20 July 2023

Summary

To ask the Secretary of State for Defence, what his Departments planned timescale for the design and construction of the Fleet Solid Support Ships beginning with the awarding of the contract to the Team Resolute consortium in November 2022.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 17 July 2023

    Written question

    To ask the Secretary of State for Defence, what his Departments planned timescale for the design and construction of the Fleet Solid Support Ships beginning with the awarding of the contract to the Team Resolute consortium in November 2022.

    Source: Commons

  2. 20 July 2023

    Answer

    On current plans, construction of the Fleet Solid Support ships will begin in 2025 with the first ship expected to enter service in 2031, and all three ships in operational service by 2032, which will deliver the Full Operating Capability for the Fleet So...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.