To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 7 September 2023 to Question 195847 on Sizewell C Power Station: Construction, what the expected value was of the Government’s shareholding in Sizewell C in the 2022

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 12 September 2023

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 7 September 2023 to Question 195847 on Sizewell C Power Station: Construction, what the expected value was of the Government’s shareholding in Sizewell C in the 2022

    Source: Commons

  2. 19 September 2023

    Answer

    The expected value of the Government’s shareholding in Sizewell C in financial year 2022-2023 (as at 31 March 2023) was a total of £363mn, made up of £11.5mn of ordinary shares and £351.8mn of shareholder loans.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.