To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 7 September 2023 to Question 195847 on Sizewell C Power Station: Construction, if she will issue a breakdown of all Sizewell C projects the Government has provided p

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 15 September 2023

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 7 September 2023 to Question 195847 on Sizewell C Power Station: Construction, if she will issue a breakdown of all Sizewell C projects the Government has provided p

    Source: Commons

  2. 25 September 2023

    Answer

    For financial year 2021-22, an investment of £100m by EDF in the Sizewell C project in January 2022 was provided by the Government through the Combined Option Agreement. In the same financial year, the Government provided a further £0.24m of innovation fu...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.