Sizewell C Power Station: Finance

answeredUnited Kingdom· UK Parliament· EN

Introduced

12 December 2024

Last action

19 December 2024 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

19 December 2024

Summary

To ask the Secretary of State for Energy Security and Net Zero, how much public investment has been directed to Sizewell C in each year since 2022.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 12 December 2024

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, how much public investment has been directed to Sizewell C in each year since 2022.

    Source: Commons

  2. 19 December 2024

    Answer

    The Government has announced funding provided to Sizewell C in the following financial years: £100m in 2021/22, £679m in 2022/23, £1,811m in 2023/24 and £1,200m in 2024/25 to date.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.