To ask the Secretary of State for Transport, whether he has made an assessment of the potential impact of not proceeding with the northern leg of HS2 on the expected demand for services on phase 1 of the project.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 16 October 2023

    Written question

    To ask the Secretary of State for Transport, whether he has made an assessment of the potential impact of not proceeding with the northern leg of HS2 on the expected demand for services on phase 1 of the project.

    Source: Commons

  2. 19 October 2023

    Answer

    The train service specification for HS2 Phase 1 services between London and Birmingham is unaffected by the decision not to proceed with the northern leg of HS2, which is therefore unlikely to impact passenger demand between London and Birmingham.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.