Summary

To ask the Secretary of State for Transport, how many and what proportion of Great Western Railway night riviera sleeper services (a) were and (b) are expected to be cancelled as a result of planned engineering works between September and November 2023.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 16 October 2023

    Written question

    To ask the Secretary of State for Transport, how many and what proportion of Great Western Railway night riviera sleeper services (a) were and (b) are expected to be cancelled as a result of planned engineering works between September and November 2023.

    Source: Commons

  2. 24 October 2023

    Answer

    From September to November 2023, the Night Riviera was scheduled to run 156 times (2 journeys a day, 6 days a week):58 of these journeys have been cancelled in full because of the re-signalling works – this is 37% of journeys. 24 journeys will start/termi...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.