Project Gigabit: North East

answeredUnited Kingdom· UK Parliament· EN

Introduced

15 April 2024

Last action

19 April 2024 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

19 April 2024

Summary

To ask the Secretary of State for Science, Innovation and Technology, whether she has made an assessment of the economic impact of delays in the Project Gigabit Lot 4 procurement process on households in the North East of England.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 15 April 2024

    Written question

    To ask the Secretary of State for Science, Innovation and Technology, whether she has made an assessment of the economic impact of delays in the Project Gigabit Lot 4 procurement process on households in the North East of England.

    Source: Commons

  2. 19 April 2024

    Answer

    The supplier that was awarded the Project Gigabit contract for the North East (Lot 4) was unable to proceed after failing to secure the funding it required. To maintain the delivery of gigabit coverage to premises in the North East, we have worked with su...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.