To ask the Secretary of State for Transport, with reference to the Answer of 4 March 2021 to Question 158968 on High Speed 2 Line: Euston Station, what the total cost of the purchase of land and property for the development of London Euston station in con

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 7 November 2023

    Written question

    To ask the Secretary of State for Transport, with reference to the Answer of 4 March 2021 to Question 158968 on High Speed 2 Line: Euston Station, what the total cost of the purchase of land and property for the development of London Euston station in con

    Source: Commons

  2. 15 November 2023

    Answer

    With reference to the 73 cases south of Hampstead Road, the total cost as of 7th November, is £995,039,073 (inclusive of VAT where relevant). The Government remains committed to delivering HS2 to Euston and set out a new ambitious development-led approach...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.