Hinkley Point C Power Station

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

7 July 2021

Last action

16 July 2021 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

16 July 2021

Summary

To ask the Secretary of State for Business, Energy and Industrial Strategy, pursuant to the Answer of 2 July 2021 to Question 21957 on Hinkley Point C Power Station, what the reason was for the delay reported by EDF in the project update statement.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 7 July 2021

    Written question

    To ask the Secretary of State for Business, Energy and Industrial Strategy, pursuant to the Answer of 2 July 2021 to Question 21957 on Hinkley Point C Power Station, what the reason was for the delay reported by EDF in the project update statement.

    Source: Commons

  2. 16 July 2021

    Answer

    The COVID-19 health crisis has had a significant impact on progress for Hinkley Point C, although construction work has continued on site. In January 2021, EDF carried out a detailed review of the schedule to estimate the impact due to the pandemic so far...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.