Summary

To ask the Secretary of State for Energy Security and Net Zero, with reference to sections 8 and 62 of the Electricity Act 1989, what his policy is on ensuring the right to public enquiry for Scottish communities in the event that a relevant planning auth

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 17 July 2024

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, with reference to sections 8 and 62 of the Electricity Act 1989, what his policy is on ensuring the right to public enquiry for Scottish communities in the event that a relevant planning auth

    Source: Commons

  2. 26 July 2024

    Answer

    Under the Electricity Act 1989, if a relevant planning authority objects to a section 36 or 37 application within the relevant time periods, Scottish Ministers must cause a public inquiry to be held and the application will be passed to the Scottish Gover...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.