To ask the Secretary of State for Defence, when the E-7 Delivery Team Leader at Defence Equipment and Support informed the senior responsible owner that the E-7 Wedgetail project was at risk.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 19 July 2021

    Written question

    To ask the Secretary of State for Defence, when the E-7 Delivery Team Leader at Defence Equipment and Support informed the senior responsible owner that the E-7 Wedgetail project was at risk.

    Source: Commons

  2. 27 July 2021

    Answer

    The E-7 Wedgetail Programme reports regularly to Ministry of Defence senior staff and Ministers through internal major project reporting systems and governance structures, including programme risks. These quarterly reports have been made since the Program...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.