To ask the Secretary of State for Health and Social Care, with reference to the Answer of 14 April 2026 to Question 120732, what the planned completion timelines are for the 40 funded schemes.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 20 May 2026

    Written question

    To ask the Secretary of State for Health and Social Care, with reference to the Answer of 14 April 2026 to Question 120732, what the planned completion timelines are for the 40 funded schemes.

    Source: Commons

  2. 4 June 2026

    Answer

    Of the 14 Urgent Treatment Centre (UTC) projects, comprising of 10 new UTCs and four UTC expansions, one scheme has already been delivered, 12 are scheduled for delivery between May and October 2026, and the final multi-year scheme is expected to be compl...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.