Ajax Vehicles: Procurement

answeredUnited Kingdom· UK Parliament· EN

Introduced

22 July 2021

Last action

6 September 2021 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

6 September 2021

Summary

To ask the Secretary of State for Defence, what the total cost of the Ajax programme is as at 22 July 2021; and what recent estimate his Department has made of that programme’s full cost at the point of completion.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 22 July 2021

    Written question

    To ask the Secretary of State for Defence, what the total cost of the Ajax programme is as at 22 July 2021; and what recent estimate his Department has made of that programme’s full cost at the point of completion.

    Source: Commons

  2. 6 September 2021

    Answer

    As published in the Infrastructure and Projects Authority Annual Report and Transparency data in July 2021; the forecast 10 year programme cost of the Armoured Cavalry programme including Ajax is £6,354 million. The bulk of the anticipated expenditure (£5...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.