To ask the Secretary of State for Transport, pursuant to the Answer of 14 March 2025 to Question 37331 on Whitchurch (Shropshire) Station: Access, what her Department's timetable is for its review of the option selection reports on step-free access at sta

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 17 March 2025

    Written question

    To ask the Secretary of State for Transport, pursuant to the Answer of 14 March 2025 to Question 37331 on Whitchurch (Shropshire) Station: Access, what her Department's timetable is for its review of the option selection reports on step-free access at sta

    Source: Commons

  2. 20 March 2025

    Answer

    The feasibility work for Whitchurch station is underway and we expect all 50 of the feasibility studies announced last year to be complete in the spring. We expect to be able to confirm which stations will move forward over the summer. The Access for All ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.