Solar Power: Infrastructure

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

17 March 2025

Last action

20 March 2025 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

20 March 2025

Summary

To ask the Secretary of State for Energy Security and Net Zero, how many solar farms have been approved as nationally significant infrastructure projects by (a) size in acres and (b) capacity in megawatts in each year since 2008.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 17 March 2025

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, how many solar farms have been approved as nationally significant infrastructure projects by (a) size in acres and (b) capacity in megawatts in each year since 2008.

    Source: Commons

  2. 20 March 2025

    Answer

    Nine nationally significant solar farms have been consented since 2008: Project(a) Approximate size in acres(b) Approximate megawatt capacityYear consentedCleve Hill Solar Park1213.29300 – 4002020Little Crow Solar Park558.461502022Longfield Solar Farm1119...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.