Summary

To ask the Secretary of State for Energy Security and Net Zero, what recent estimate her Department has made of when the (a) Hinkley and (b) Sizewell nuclear power plant will be operational.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 27 November 2023

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, what recent estimate her Department has made of when the (a) Hinkley and (b) Sizewell nuclear power plant will be operational.

    Source: Commons

  2. 30 November 2023

    Answer

    EDF is the lead investor at Hinkley Point C and they have provided a target date for commercial operations for Unit Reactor 1 of June 2027, with Unit Reactor 2 following a year later in June 2028. Both units have a risk of a delay of 15 months. We expect ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.