To ask the Secretary of State for Defence, what approvals process is required for the Merlin Out of Service Date Extension Programme; and what the timescale is for that process.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 24 March 2025

    Written question

    To ask the Secretary of State for Defence, what approvals process is required for the Merlin Out of Service Date Extension Programme; and what the timescale is for that process.

    Source: Commons

  2. 27 March 2025

    Answer

    The Royal Navy’s Merlin helicopter Out-of-Service Date Extension Programme, to retain the capability in service from 2029-30 until 2040, is currently underway through standard Ministry of Defence processes. The Outline Business Case was approved in Octobe...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.