To ask the Secretary of State for Defence, what his timeframe is for completing the construction of the PEGASUS facility.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 10 May 2022

    Written question

    To ask the Secretary of State for Defence, what his timeframe is for completing the construction of the PEGASUS facility.

    Source: Commons

  2. 18 May 2022

    Answer

    The original and current approved costs and the current in-service dates for Project Mensa and Project Pegasus are as follows: ProjectOriginal Cost Approved in 2011Current Approved CostApproved In-service DateMENSA£734 million£1996 million2024PEGASUS£634 ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.