United Kingdom · Question · Written question

UIN 44833

High Speed 2 Line

answeredUnited Kingdom· UK Parliament· EN

Introduced

7 April 2025

Last action

28 April 2025 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

28 April 2025

Summary

To ask the Secretary of State for Transport, what her Department's original budget for HS2 Phase 2 was; how much her Department has spent since that project started; and what the estimated final cost is in (a) real and (b) current terms.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 7 April 2025

    Written question

    To ask the Secretary of State for Transport, what her Department's original budget for HS2 Phase 2 was; how much her Department has spent since that project started; and what the estimated final cost is in (a) real and (b) current terms.

    Source: Commons

  2. 28 April 2025

    Answer

    The original funding envelopes (in 2015 prices) for Phase 2a was £3.72bn and £24.8bn for Phase 2b. Spend on the HS2 project can be found in the latest Parliamentary Report here , which is updated and published at regular intervals. The project currently r...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.