PoliticalRepoPoliticalRepo

United Kingdom · Question · Written question

UIN 45

AWE: Construction

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

10 May 2022

Last action

18 May 2022 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

18 May 2022

Summary

To ask the Secretary of State for Defence, what the (a) original and (b) current cost expectations are for the (i) MENSA and (ii) PEGASUS projects.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 10 May 2022

    Written question

    To ask the Secretary of State for Defence, what the (a) original and (b) current cost expectations are for the (i) MENSA and (ii) PEGASUS projects.

    Source: Commons

  2. 18 May 2022

    Answer

    The original and current approved costs and the current in-service dates for Project Mensa and Project Pegasus are as follows: ProjectOriginal Cost Approved in 2011Current Approved CostApproved In-service DateMENSA£734 million£1996 million2024PEGASUS£634 ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.