Summary

To ask the Secretary of State for Defence, what recent progress his Department has made on implementing the Submersible Ship Nuclear AUKUS programme.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 23 April 2025

    Written question

    To ask the Secretary of State for Defence, what recent progress his Department has made on implementing the Submersible Ship Nuclear AUKUS programme.

    Source: Commons

  2. 30 April 2025

    Answer

    The SSN-AUKUS programme is approximately 18 months into the Detailed Design and Long Lead (D2L2) phase, with contracts totalling around £4 billion having been placed in October 2023. Infrastructure improvements are also being made at BAE Systems’ shipyard...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.