To ask the Secretary of State for Transport, what recent discussions he has had with National Highways on (a) the expected completion date for works on the Painshill junction of the M25 and A3 and (b) the steps being taken to (i) ensure the timely complet

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 9 September 2024

    Written question

    To ask the Secretary of State for Transport, what recent discussions he has had with National Highways on (a) the expected completion date for works on the Painshill junction of the M25 and A3 and (b) the steps being taken to (i) ensure the timely complet

    Source: Commons

  2. 12 September 2024

    Answer

    National Highways are due to complete the main works at the Painshill roundabout and junction 10 of the M25 by Summer 2025 however, there will be other minor works including environmental enhancements that will be completed towards the end of 2025. To ens...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.