To ask the Secretary of State for Defence, what is the (a) original and (b) current cost expectations for the Dreadnought programme.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 8 September 2022

    Written question

    To ask the Secretary of State for Defence, what is the (a) original and (b) current cost expectations for the Dreadnought programme.

    Source: Commons

  2. 22 September 2022

    Answer

    The 2015 Strategic Defence and Security Review estimated that the Dreadnought programme is likely to cost a total of £31 billion (including inflation, over the lifetime of the programme) and set a contingency of £10 billion. The programme remains within i...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.