National Grid: Costs

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

10 September 2024

Last action

8 October 2024 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

8 October 2024

Summary

To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 10 September 2024 to Question 4389 on National Grid: Costs, whether (a) he and (b) Ofgem is able to provide the estimate requested.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 10 September 2024

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 10 September 2024 to Question 4389 on National Grid: Costs, whether (a) he and (b) Ofgem is able to provide the estimate requested.

    Source: Commons

  2. 8 October 2024

    Answer

    New network infrastructure is essential to meet the rising demand for electricity and connect new renewable generation. Ofgem estimates that the Western Link and Eastern Green Link will increase consumer bills by an average of £6.50 per annum over a 60-ye...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.